Official status
What the responsible institution says
PBIA Tracker keeps the original plan, later changes and delivery evidence on separate tracks. No progress scores. No silent assumptions.
54 baseline actions registered
1 priority action deeply reviewed
What the responsible institution says
What public records can support
Compared with the original deadline
Sum of budgets extracted into tracked baseline actions. Not an execution total.
The current machine page describes a live, configured system with approximately 20 PFLOPS of installed capacity.
LNCC's formal annual report again records a US$19.4 million contract with Eviden, the November delivery and the expansion's status as PBIA's first stage.
A signed amendment replaced the proposed cooling solution, reduced the global contract value to R$2,424,569.49 and extended the term to 140 days from contracting and purchase order.
The expanded system appeared at position 89 in the November 2024 TOP500 list, short of the plan's Top 5 target.
LNCC recorded delivery of more than 20 tonnes of equipment in three trucks.
“An official claim is a record.
It is not, by itself, a delivered result.”
We preserve original promises, label uncertainty, and separate planned, authorized, committed, contracted and paid money.
Read the methodology →