LNCC reports approximately 20 PFLOPS installed
The current machine page describes a live, configured system with approximately 20 PFLOPS of installed capacity.
Planned targets and source-backed events stay on separate visual tracks.
The current machine page describes a live, configured system with approximately 20 PFLOPS of installed capacity.
The later publication retains the Top 5-in-five-years promise and R$1.8 billion projection, while explicitly identifying investments already underway and new LNCC expansion investments as action components.
LNCC's formal annual report again records a US$19.4 million contract with Eviden, the November delivery and the expansion's status as PBIA's first stage.
A signed amendment replaced the proposed cooling solution, reduced the global contract value to R$2,424,569.49 and extended the term to 140 days from contracting and purchase order.
The expanded system appeared at position 89 in the November 2024 TOP500 list, short of the plan's Top 5 target.
LNCC recorded delivery of more than 20 tonnes of equipment in three trucks.
LNCC's delivery notice explicitly described the 17 PFLOPS update as the first stage of PBIA. This links a pre-launch contract to the plan without equating it to the full Top 5 promise.
LNCC and Eviden teams completed the final acceptance test for six BullSequana XH3000 racks in France.
FACC and Bull signed a R$5.5 million contract, with LNCC as intervening party, for chillers and Ecodry equipment under Petrobras cooperation term 0050.0124080.23.9.
The baseline plan sets a five-year target for updating Santos Dumont into the five largest systems on TOP500, with R$ 1.8 billion in projected resources.
LNCC announced an agreement with Eviden for a 17 PFLOPS expansion. This predates the public PBIA launch and was later described as its first stage.